The Barrington School Committee has awarded the bid to renovate the Victory Field athletic complex to Green Acres Landscape and Construction Company, of Lakeville, Mass.
Green Acres …
This item is available in full to subscribers.
Please log in to continue |
Register to post eventsIf you'd like to post an event to our calendar, you can create a free account by clicking here. Note that free accounts do not have access to our subscriber-only content. |
Are you a day pass subscriber who needs to log in? Click here to continue.
The Barrington School Committee has awarded the bid to renovate the Victory Field athletic complex to Green Acres Landscape and Construction Company, of Lakeville, Mass.
Green Acres officials submitted a bid to complete the project for $4.23 million. The bid also listed seven alternatives — two were for potential project reductions and five were for additions.
Green Acres was one of three companies to bid for the project.
Green Acres’s bid was the second-lowest — Yardworks’s bid was $4,075,444, and RICON’s bid was $5,019,583.40.
Money from the school department’s capital reserve account will pay for the project.
The consulting firm LeftField provided members of the Barrington School Committee with a recommendation.
“After an in-depth review of the Victory Field bid estimates which included some scope reduction to meet budget and second request for pricing from all contractors, we suggest awarding the project scope to Green Acres Landscape and Construction Company,” wrote Chris Dunphy, of LeftField.
The recommendation was based on several factors, Dunphy wrote.
“They have an established work history in field replacement, with the design engineer of Victory Field, Nesra Engineering,” he wrote.
Dunphy added that Green Acres has completed many projects that are comparable to the Victory Field renovation — in scope, size and cost. He listed Rhode Island projects Smithfield High School, Portsmouth High School, and Wheeler School, and Massachusetts projects Fairhaven High School, New Bedford High School, North Attleboro High School, and Mashpee High School as examples.
In addition, Green Acres’s proposed construction schedule was more favorable than those of the other bidders “and they have a proven track record for meeting project deadlines.”
Bid information from Green Acres included a project completion date of Sept. 22, with a close-out date of Oct. 9.
Yardworks bid to complete the project by Oct. 10 and the close-out date of Oct. 21. RICON bid to complete the project by Dec. 15 with a close-out date of Dec. 29.
Work is expected to begin this spring.
Dunphy wrote that the low bidder, Yardworks, did not present comparable completed projects and “missed on some of the key scope in their initial bid…”
March 13 meeting
Members of the Barrington School Committee and LeftField’s Chris Spiegel and Chris Dunphy discussed the project bids during the March 13 meeting.
Committee Chairman TJ Peck said he agreed with LeftField’s recommendation that Green Acres’ bid was the best proposal of the three. Peck also shared some of the details about the project — he said the bid specifies the use of Pivot synthetic turf, which does not have PFAS and its production process does not include PFAS. PFA is a chemical compound that is often used in the production of plastics and has been found to be dangerous to humans. Peck said Pivot turf offers a 12-year warranty and does not require any infill.
Peck said field maintenance was expected to be minimal and could likely be handled by the custodial staff at the high school. He said maintenance would consist of cleaning organic material, such as leaves, off the synthetic turf and could be done with blowers or fans.
Peck also spoke about the plans for the new running track. He said that at the recommendation of the school’s director of athletics, a higher quality track surface would be used.
Dunphy added that the track at Barrington High School would be similar to tracks used at the collegiate level.
“You’re definitely getting a better product,” Dunphy said.
Peck said the estimate to replace the synthetic turf surface is $1.1 million, dispelling some residents’ concerns that the replacement would equal the initial construction cost.
Peck said the total price of the project was $4.6, which includes about $400,000 in owner-controlled soft costs.
Peck asked Barrington Schools Finance Director Doug Fiore how much money would be left in the district’s capital reserve account if the $4.6 million was spent on the Victory Field renovation project. Fiore said there would be $2 million remaining in the account.
Peck thanked the community for voicing their concerns surrounding the project. He then made a motion to award the construction bid for the Victory Field athletic complex renovation to Green Acres Landscape and Construction. Karen Rasnick seconded the motion, which passed 5-0.
Peck also made a motion to approve the expenditure of $4,653,707 from the district’s capital reserve account for the project. Rasnick seconded the motion, which passed 5-0.