Some will see it as a home run ruling, while others might say the umpire needs glasses. Regardless, going to a ballgame in the not-so distant future will be a much more convenient, cozy experience …
This item is available in full to subscribers.
Please log in to continue |
Register to post eventsIf you'd like to post an event to our calendar, you can create a free account by clicking here. Note that free accounts do not have access to our subscriber-only content. |
Are you a day pass subscriber who needs to log in? Click here to continue.
Some will see it as a home run ruling, while others might say the umpire needs glasses. Regardless, going to a ballgame in the not-so distant future will be a much more convenient, cozy experience for the Mt. Hope High School community, especially for the players and the student body.
Despite the united opposition of the members representing one of the towns, the Bristol Warren Regional School Committee on a 6-3 tally recently approved adding an alternate item to the district-wide school construction project for the construction of a new baseball field on the Chestnut Street campus.
The vote was taken at the committee's November 9 meeting held in the MHHS cafeteria with a larger than usual crown and went along town lines.
The three Warren members — Nicky Piper, Kyle Jackson and Christine Barlow — all voted against the expenditure not to exceed $3.657 million for the diamond, citing the budgetary difficulties the town continues to face as a result of a lawsuit settlement along with reductions in school aid from the state.
The six Bristol members — Chairman Adam McGovern, Jessica Almeida, Glenn Donovan, Megan Ferreira, Margaret Richards and Carly Reich — each voted in the affirmative, though many said they sympathized with the position taken by their colleagues from the north.
The monies for the diamond derive from the $10 million contingency fund included in the $186 million budget for all of the construction taking place around the district.
Nick Hull, a representative of the district's construction project manager PMA Consultants, told the committee to date during the roughly 18 months of work only some $700,000 of the set-aside had actually been used while the project has existing exposure of about $2.353 million more.
The approved figure for the field was significantly above the estimate provided to committee at one of its meetings this past October. Then, Hull quoted the amount to build was $2.54 million.
Hull, after being questioned on the topic by Almeida, explained since that time a new electrical firm was required to be hired as a subcontractor, which accounted for most of the increase. There was also a slight modification in the materials needed to fill the location of the diamond, which will be situated near what is now the front entrance to the existing school.
Later in the discussion, Hull, McGovern and Superintendent Ana Riley each discussion to some specificity the idea of "risk." In essence, if the item wasn't approved at the meeting and put on the construction schedule then it would likely only increase in cost and might not be able to be added into the construction schedule due to timing and funding limitations.
Prior to the vote, the board heard from several members of the public who advocated for the field, including current head coach of the MHHS program, Manny DaSilva. DaSilva used the mantra, "athletic equity," in urging the committee to approve the added expenditure.
DaSilva, a three-sport standout while attending the old Bristol High School back in the late 1980s before the merger, said the program's home at Guiteras Field, owned by the Town of Bristol, was outdated and lacked even rudimentary aspects like electrical connections. He noted what would be an inherent disparity of programs that will use the athletics stadium, tennis courts and softball field being built on campus as part of the new MHHS project while baseball remained off campus at a dated facility.
One of the speakers who spoke in opposition to the field suggested the committee could instead renovate Guiteras at a fraction of what the new one would cost. McGovern countered by saying some of the same concerns about flooding and drainage stated about the MHHS property would be relevant at the Guiteras as well.
Warren Town Councilor Derrik Trombley spoke during the comment period, asking the committee to consider his town's financial plight while urging a vote against the measure.
Trombley lauded the committee for keeping to the $186 million overall budget and for keeping the overall project on time, though added, "But even with that, the financial strain on the Town of Warren is very significant, and to add this additional expense concerns me as to what it's going to do to impact the budget of the Town of Warren. So as a steward of them, I'm here tonight to ask you to not move forward at this time."
In voicing their dissent Piper and Barlow, specifically, referred to their lobbying of constituents to pass the school bond at the special election held in the spring of 2024. It was short thereafter, the town's insurer settled a $13 million lawsuit brought against Warren, $8 million of which it was forced to pay out of its coffers.
Because of that, Warren's finances have been mired in disarray ever since. And now it faces 30 annual payments for the construction bond, the first one estimated earlier this calendar year to be $1,384,338 in Fiscal Year 2027-28.
Piper suggested the Warren Town Council may have to petition the state to exceed the 4% cap on annual increases to the property tax rate by more than double just to meet its necessary obligations for FY27-28.
They, along with Jackson, said they could not support adding to the tally their constituents might be responsible for, even though it is coming from the existing overall project budget.
"My job is to push for whatever is best for the kids. And absolutely, this baseball field on campus is best for the kids. However, I do not know how it is sustainable if we are to get a 10% property tax increase," said Piper.
Barlow, as did Richards at one point, asked if it wouldn't be more prudent for the committee to delay a vote on the field until later in the process. Riley said it wouldn't be feasible to do so.
"I would not recommend we wait. We cannot wait until the project's over. We need to go out to bond this spring," said Riley, noting the state required all elements of the MHHS project must be "substantially complete" by June 30, 2027.
Donovan's remarks on the matter seemed quite pertinent. Prefacing his comments by acknowledging he has a son who plays baseball, he said, "It would be, I think, a real tough pill to swallow to see the baseball program be left out of all these improvements."
And though noting Warren's plight, Donovan added, "I don't want to diminish it, but I just think that it's worth making the investment now, and really not having any regrets looking back at what else we could have done to improve the project in the end."
Said Reich, "This has been a really tough decision, and I appreciate all the time and thoughtfulness my fellow committee members have put into this. But at the end of the day, Glenn, what you were sort of saying, it's like thinking about saving money now. I mean, for goodness sake, what's the best time to build anything? Yesterday. I think even though the initial impact on Warren will be hard and difficult, and puts other people at risk if we wait longer, prices go up, potentially."
Before requesting a roll call vote, McGovern explained how he saw the notion of risk involved with district-wide construction as three-fold. The first was when they excavated for the new building, finding just an old oil tank submerged. The second was with the other projects at the elementary and middle school buildings, which was minimal and accounted for most of the $700,000 contingency spend. The third is with demolition of existing MHHS, which in his estimation worst case would cost a few million, still leaving a substantial amount in the contingency even with the baseball field included.
"My number, my super, super conservative number's been $2 million. I think it's way over the top, but that's been my number," McGovern added. "The absolute worst, like, the worst thing you could find, where we have to start shipping soil out of here, $2 million. We're still under this project bike, $2 million or so, $2 to $3 million. And in my personal mind, I think that would be a victory. We would still be under budget."
After the meeting, DaSilva was chuffed about the support the program received by the many in attendance that evening as well as the action of the board.
"I think it's fantastic the school committee made the right decision for the school and the community for generations to come," DaSilva said. "Baseball finally has a place on campus to call home."