Not one of the 100-plus residents in the audience wanted it to happen, and by the time the up-or-down vote was taken after 10 p.m., it was clear that none of the members of the planning board did so …
This item is available in full to subscribers.
Please log in to continue |
Register to post eventsIf you'd like to post an event to our calendar, you can create a free account by clicking here. Note that free accounts do not have access to our subscriber-only content. |
Are you a day pass subscriber who needs to log in? Click here to continue.
Not one of the 100-plus residents in the audience wanted it to happen, and by the time the up-or-down vote was taken after 10 p.m., it was clear that none of the members of the planning board did so either.
But the master plan phase for the proposed 80-room hotel on Gooding Avenue was “approved” by the board on Thursday, March 5, and the project will now move on to the preliminary phase.
The public hearing was held in the Colt School auditorium to handle the anticipated crowd, which took turns speaking for over two hours, objecting to every element of the proposed project, from the environmental impact, hotel aesthetics, wildlife welfare, flooding, traffic and public safety, excessive noise, assertions made on erroneous soil information, flood lights, quality of life impact, car collisions with deer and not fitting into Bristol’s Comprehensive Plan.
The board debates
After the public hearing closed, the board picked up the conversation, reflecting many of the same concerns.
Board member Mike Sousa noted that he found it difficult to make a decision until the board got answers from a town consultant who could address some of the environmental issues that were raised.
“We can't conflate comprehensive plan consistency with environmental impacts,” said town solicitor Amy Goins. “You have an application here…the DEM has already issued the wetlands permit. That finding has essentially been satisfied for you by the state.
On comprehensive plan consistency, this (development) is by right with no zoning relief required. The hotel is permitted by right.”
Goins also noted that requesting a fiscal impact statement at the master plan phase is unusual.
“It is not typical that a use permitted by right is required to submit a fiscal impact statement at the master plan stage,” said Goins. “I do think it's appropriate for the board to dig in at the next stage.”
Sousa expressed concern about the expectation that the hotel would enjoy 70% occupancy, the oft-cited threshold for financial viability.
“What if it's determined that the board feels like 40 units is more likely to realize a 70% occupancy rate which would satisfy the financial restrictions that the applicant put on themselves in terms of what's viable or not viable?” said Sousa.
He continued, “That's a major change between concept and preliminary. You're not going to develop engineered plans for an 80 room hotel and then all of a sudden at preliminary, after they spent all this money and effort, say we don't think we can approve that. We would rather approve a 40-room hotel, which changes everything. So how can that not be appropriate at master?”
Goins responded, “We don't typically require the applicant to produce proof at master plan that the market needs whatever the use is. To the extent there's concerns based on the local history (of hotels in Bristol), it's appropriate for you to get into that. To the extent that the board would feel more comfortable with a hotel that is more boutique, a smaller hotel. That's an appropriate conversation for you to have.
“I would prefer you frame it as requesting that the applicant come back at the next stage with plans for a smaller hotel and with a market analysis that shows a plan B.”
Acting board chairman Steve Katz interjected, “That's exactly what I had suggested at the TRC (Technical Review Committee meeting). If we go forward with this and we decide to approve with conditions, I will want to see plans that show a hotel of no more than 40 rooms, no more than two stories high and it must have a New England look to it.
“And I don't want to have a three-story hotel where people staying in these rooms are looking down at people's backyards that have little children and so on. That is unacceptable to me and I will not support that.”
Additional conditions mentioned by the board included a new traffic study that's done during the spring and summertime in the daylight (the original one was performed late in the day, offseason), as well as pervious pavement to facilitate the pace of water infiltration.
Board member Brian Clark brought up the issue that is forefront for so many residents who have seen hotels come and quickly go, leaving behind an eyesore, student housing, or worse.
“What's the second life of this building once it's no longer a hotel?” asked Clark, citing examples of the state using defunct hotels as housing, and the assorted problems that have come hand-in-hand with that practice.”
Added board member Jessalyn Jarest, “I’m still struggling to find how this fits with the comprehensive plan. Page one of our comp plan, the vision statement says, ‘each Bristol resident will feel that they are a part of a long history of careful and people-oriented town building.’ There's been a lot of people that have come out against this. In the no category, we have 45 letters against, and a petition that over 120 people have signed. There's only been one person that's for it.
“We've had people speaking who are scientists, who are who are wetland biologists, who are part of the Conservation Commission, the Land Conservation Trust, Save the Bay. And I’m really struggling to find how this is fitting with that component of the comprehensive plan.”
“I thought the state had made an error in granting this permit. I still feel that way today,” said board member Richard Ruggeiro. “And I think what the state has done to many of the communities and is continuing to do is to deplete the authority that the locals have.
“I’m sitting here as a member of the planning board and whatever the decision I make means nothing because the state has taken that authority away from us.
“I firmly believe that we as a town need to challenge this application, and we need to challenge the decision that the DEM made.”
Ruggeiro went on to read from the 2016 DEM permit denial by Martin Wencek, Wetlands Program Supervisor. Wencek would ultimately approve the permit in 2024.
This prompted an immediate response from Sousa.
“Marty Wencek is a stand-up engineer. That (2016) was a totally different plan,” said Sousa. “So stop inciting the public needlessly and and leading them down a road that is not making any sense.”
“I can't take this,” Ruggeiro replied. “I’m not going to sit here and be insulted by someone on the same board that I sit on. And I'm not inciting anyone.”
“We're getting off topic,” said Katz, “because the applicant did not have to have a DEM permit to do master plan. This should been done at preliminary. We should not even be having this conversation now.”
“Are you telling me that I can't deny this request?” said Ruggeiro.
“You are free to do whatever you feel you need to do,” said Katz. “But making a decision based upon this wetlands permit is improper. Whether it was done correctly, whether it was done based on false pretense, I don't know. My point is it's irrelevant for making a decision on master plan.”
Michael Resnick, the attorney for the developers, then weighed in the conversation, noting that he would object on his client’s behalf to a couple conditions that had been mentioned that evening.
“One is the revised plan for 40 unit hotel,” Resnick said. “Respectfully, that's not this application. We could certainly have preliminary and leading up to the preliminary and add a TRC talk about a reduction in the density of the development.
“I don't believe that this board can compel my client to design a project that they're not building and that they didn't ask for.
“We don't need any relief from height. We don't need relief from any of the regulations…And the project we've designed is a 80 units. So, we're not going to spend the time or the money to revise the plan set for 40 units because we're not building 40 units and it would be a waste of our money and your time.”
He continued with the proposed condition that the developer do a market analysis.
“I genuinely question the ability of the board to compel a market analysis of our proposed hotel and also a 40 unit, which is your choice.
“You can pass those as conditions, if we're lucky enough to get an approval, but I'm going to have to talk to my client and my understanding as we sit here today is that they're not acceptable.”
“We may not be unanimously in agreement at master plan, but we may agree to go forward with this at master plan,” said Katz. “But when we get into preliminary, that's when we have the back and forth, the negotiation, what we want for this town, where it fits in this town.
“And I can tell you right now, and I'll go on the record, I will not agree to an Irvine California-looking hotel that looks down somebody else's yard.”
“I just I can't agree to a condition at master plan to build a product that's not before you or to do a market analysis about one that's not before you,” said Resnick. “If you want to have those discussions at preliminary, of course, all developments have the potential of losing unit counts at preliminary. And we will go for that exercise and I have to tell you I think that we can come to something that's reasonable.”
With 10 minutes remaining, the board had two options: a vote, or a continuance. However, a continuance would have to be scheduled for after the established deadline for making a decision. Goins advised the board to take the vote.
The solicitor also warned the board about the hazard of a down vote at this stage.
“I just want to make sure you know if it's appealed it may not come back to you. If the board denies it and if the court reverses that decision, the effect could be that they have a master plan approval without conditions. So, you might see it come back at preliminary, but there would be no conditions of approval,” said Goins.
“That’s why I am leaning towards approving this,” said Katz, “recognizing the master plan is only conceptual and we put the conditions that we want to see.”
“You need a written decision, so the vote tonight would be to direct staff and legal to prepare a written decision for the board's review,” said Goins. “If that motion is made, you would want the recommended conditions of approval plus potentially more conditions of approval.”
“Okay,” said Katz, “I’m in favor of making a motion to approve the applicant’s master plan as a conditional approval predicated upon the conditions that we choose.
“And again folks, this is a conceptual plan. It is not a design and build plan. It is not the preliminary plan. It doesn't have the engineering drawings. It should not have had the DEM permit, though it did.
“We cannot deny it because they want to build it in the wetlands. We cannot deny because they have a permit now. We cannot deny because they have a legal right to build it in that location. So, I am torn on how else to deny their master plan conceptual application. Legally, I don't see a way to do that. But we can put conditions on it for the preliminary.”
“So if the board denied the application, what happens after that?” asked Ruggeiro.
“You have to have a reason for denying it; you need to articulate the reason for the motion. I need more than just motion to approve or motion to deny in order to reflect a decision that reflects the will of the board and isn't simply something I came up with,” said Goins.
At last, a motion and a vote
“I will make a motion to approve a conditional approval of this master plan that will include all of the conditions that we had stipulated back at the TRC. I also wanted to add deed restriction.” said Katz.
After a prolonged silence, Clark seconded the motion.
“I think that if we don’t, this is very tricky. We all want what's best for the town,” said Jarest.
“The dilemma in my head is if we vote no, it could be appealed, then we don't have any stipulations, said Sousa. “Then it gets approved because the DEM already overruled all of our governing authorities….We don't have any option to get what's right for Bristol. It gets the appeal, they get approval, they do whatever they want.”
“I will add to what Mike just said, if we deny…we will be sued,” said Katz. “And it will be an expensive lawsuit. And we will likely lose that lawsuit. So we will be paying taxpayer dollars to carry that lawsuit, pay their legal fees, and like Mike said, we'll be stuck with a result that is not in the best interest of the town of Bristol.
“So I'm looking at the opportunity to try to mediate this and go into the preliminary plan, which is the actual plan, the detailed plan, where we can provide guidance to make it fit within the town.
Katz continued, “Look, folks. The five of us are here because we love this town. We're trying to do what's best for this town. And we do not vote or make decisions simply because the developer wants us to do it.”
The motion passed 4-1, with Jarest and Sousa joining the majority, and Ruggeiro voting against.
The written decision, including conditions, will be prepared by the solicitor in time for the board’s review and approval at its April meeting.