Out with the old … Demolition crews tear into contaminated middle school

Posted 12/31/18

They had nibbled away at the front entrance and dug up PCB tainted soil around the foundation, but last week heavy equipment ripped into the middle school itself.

With the elementary school closed …

This item is available in full to subscribers.

Please log in to continue

Log in

Register to post events


If you'd like to post an event to our calendar, you can create a free account by clicking here.

Note that free accounts do not have access to our subscriber-only content.

Day pass subscribers

Are you a day pass subscriber who needs to log in? Click here to continue.


Out with the old … Demolition crews tear into contaminated middle school

Posted

They had nibbled away at the front entrance and dug up PCB tainted soil around the foundation, but last week heavy equipment ripped into the middle school itself.

With the elementary school closed for vacation next door, the Christmas break offered a traffic-free opportunity to get a bit of the heaviest, noisiest work out of the way. There will be much more of that to come, however.

Work began in earnest off Old County Road on December 26, the day after Christmas and continued through week’s end.

It’s a bit later than had been hoped. Before actual demolition could begin, crews first had to deal with the PCBs that were the primary reason behind the decision to close the middle school and build a new grade 5-12 school roughly in its place.

While they were carefully removing everything that PCBs were known to inhabit —ceiling and floor tiles, window frames and more — and shipping them off to a secure landfill, they found yet another toxin.

This one, 2-methylnapthalene, proved to be in isolated locations in minor amounts and is expected to generate an added bill of around $20,000 (money that has already been appropriated).

Offsetting that expense, however, is the fact that well drillers found sufficient good quality water at shallower depths than had been feared which has proven to be a money saver.

There is much more demolition to go on the huge structure and all of that debris must be trucked away. That truck traffic is being scheduled and routed to minimize impact on morning and afternoon arrival and dismissal times at the elementary school next door.

The School Building Committee now predicts that the demolition phase will last until sometime in early March.

The yet-to-be-selected general contractor will begin setup in April and construction should start in May on the $97-plus million job.

Students should be able to move into their new school in 2021.

2024 by East Bay Media Group

Barrington · Bristol · East Providence · Little Compton · Portsmouth · Tiverton · Warren · Westport
Meet our staff
Jim McGaw

A lifelong Portsmouth resident, Jim graduated from Portsmouth High School in 1982 and earned a journalism degree from the University of Rhode Island in 1986. He's worked two different stints at East Bay Newspapers, for a total of 18 years with the company so far. When not running all over town bringing you the news from Portsmouth, Jim listens to lots and lots and lots of music, watches obscure silent films from the '20s and usually has three books going at once. He also loves to cook crazy New Orleans dishes for his wife of 25 years, Michelle, and their two sons, Jake and Max.